Rip Rap Installment Lock and Dam 25 Spillway Upper Mississippi River mile 241.2

  1. Rip Rap installation at Lock 25 Spillway is scheduled to start on 24 August 2015 at 18:00 hours and complete by 25 September 2015 at 17:00 hours.
  2. Contractor shall be utilizing floating plant downstream of Lock and Dam 25 for delivery and placement of rip rap on the LD 25 Overflow Dike located on the Illinois side of the River.
  3. Floating plant shall be positioned on the Illinois side of the Mississippi River. Floating plant shall not cause any impacts to Navigation and no Lock closures shall be required.
  4. Tow boats, MV Wayne B. Smith and MV Chattie Sue Smith can be contacted on Marine Channel 82 if needed.

FOR THE DISTRICT ENGINEER:
//signed//
Andrew C. Schimpf, P.E.
Rivers Project Manager

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s